Texas data-centre feed
What changed
large load interconnection: LLI-2011.
critical it capacity: 1,400 MW critical IT campus capacity.
planned campus capacity: 540 MW planned campus capacity across six facilities.
contracted it: 70 MW contracted critical IT to AWS.
approved interconnection: 100 MW gross ERCOT-approved interconnection.
support generation: 366 MW ERock generation facility under construction for El Paso Electric.
campus demand: Approximately 1,000 MW announced campus demand.
contracted power: 400 MW contracted powered-land capacity: 190 MW Phase 1 + 210 MW Phase 2.
available power: 115 MW power capacity stated available by Oracle.
Hood County powered industrial site: Acquisition completed through a 50/50 Big Digital Energy / 10NetZero joint venture on 2026-07-20..
Abernathy Joint Venture: TeraWulf entire 50.1% membership interest was sold effective 2026-07-06; TeraWulf no longer holds equity in the Abernathy JV..
Hood County site: Phased expansion to as much as 111 MW of grid capacity is explicitly subject to ERCOT validation..
QTS FTW1 DC1 Expansion: TDLR TABS2026022992 records a 147,946 sq ft expansion with scheduled 2026-07-01 start and 2027-10-01 completion; registration does not prove physical start..
Hood County site: Existing natural-gas infrastructure could support behind-the-meter generation and total buildout up to 300 MW; potential total power only, not contracted, grid-secured, IT-load or energized MW..
Hood County site: Issuer states the acquired site currently has 17 MW of operational power; this is site power, not energized data-centre IT load..
planning envelope acres: 1,522.18 acres (Goodland Light Industrial zoning/planning envelope; not a fee-ownership or data-center footprint assertion).
CyrusOne Medina County campus power path: CyrusOne states the campus is to be served through dedicated transmission infrastructure designed specifically for the facility and funded by CyrusOne, with project transmission interconnection and power-delivery costs paid by CyrusOne. Exact serving agreement and project MW remain unverified..
CyrusOne Medina County campus physical progress: CyrusOne states site preparation and grading are in progress and describes early earth-moving/grading work with the general contractor. This supports construction-stage physical site work but not commissioning or energization..