Texas data-centre project

CyrusOne SAT14A / Castroville data center

Castroville, Medina · construction. Source-backed view of project status, participants, power and development evidence.

constructionCastrovillePRC-065
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
1Sources
3Verified facts
8Recent updates
0Phases tracked

Decision brief

What changed

Latest source-backed movement
Research question opened for PRC-065

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Research question opened for PRC-065

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-065

Project has no verified linked evidence. What authoritative evidence resolves this?

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Grid positionCyrusOne states the campus is to be served through dedicated transmission infrastructure designed specifically for the facility and funded by CyrusOne, with project transmission interconnection and power-delivery costs paid by CyrusOne. Exact serving agreement and project MW remain unverified.
grid infrastructure

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

8 updates
Research question opened for PRC-065

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Research question opened for PRC-065

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-065

Project has no verified linked evidence. What authoritative evidence resolves this?

Advanced project has no canonical phase records

PRC-065 requires analyst attention: advanced status without phases.

Project has no verified linked evidence

PRC-065 requires analyst attention: missing linked evidence.

Advanced tracker status lacks evidence-backed status history

PRC-065 requires analyst attention: advanced status without history.

Verified project fact updated

CyrusOne Medina County campus power path: CyrusOne states the campus is to be served through dedicated transmission infrastructure designed specifically for the facility and funded by CyrusOne, with project transmission interconnection and power-delivery costs paid by CyrusOne. Exact serving agreement and project MW remain unverified..

Verified project fact updated

CyrusOne Medina County campus physical progress: CyrusOne states site preparation and grading are in progress and describes early earth-moving/grading work with the general contractor. This supports construction-stage physical site work but not commissioning or energization..

Current position

Verified facts

3 verified
grid infrastructureCyrusOne states the campus is to be served through dedicated transmission infrastructure designed specifically for the facility and funded by CyrusOne, with project transmission interconnection and power-delivery costs paid by CyrusOne. Exact serving agreement and project MW remain unverified.
construction statusCyrusOne states site preparation and grading are in progress and describes early earth-moving/grading work with the general contractor. This supports construction-stage physical site work but not commissioning or energization.
site control recordMedina County's executed Chapter 312 agreement names CyrusOne LP and identifies approximately 244.3 acres in Precinct 2 as the project property for one or more data centers and related infrastructure.