Project has no verified linked evidence. What authoritative evidence resolves this?
Texas data-centre project
PowerHouse Texas campus (768-acre claim; "Red Oak" alias disputed)
Candidate parcel 181262: 881 Miller Rd, Midlothian situs; City of Grand Prairie taxing/planning jurisdiction. "Red Oak" remains a disputed project alias., Ellis · identified. Source-backed view of project status, participants, power and development evidence.
Decision brief
What changed
unambiguous high-confidence primary-source finding
plausible finding requires review before changing canonical project state
Power & capacity
MW without the ambiguity
Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.
Latest intelligence
Project change log
Project has no verified linked evidence. What authoritative evidence resolves this?
unambiguous high-confidence primary-source finding
plausible finding requires review before changing canonical project state
planning envelope acres: 1,522.18 acres (Goodland Light Industrial zoning/planning envelope; not a fee-ownership or data-center footprint assertion).
Grand Prairie Building 1 schedule: The current TDLR registration lists Building 1 construction through April 2028, superseding the developer's original May 2026 first-power target as the operative public construction schedule for this building. No energized MW is evidenced..
Initial Grand Prairie power tranche: PowerHouse stated that the first 500 MW tranche had been approved through ERCOT. No customer-specific interconnection agreement or energization record is attached to this claim, so it is not classified as contracted or energized MW..
PowerHouse / Provident Grand Prairie campus: PowerHouse announced a planned 1.8 GW switchyard for the Grand Prairie campus. This is a developer-stated ultimate scale and is not classified as contracted, grid-secured or energized MW..
AREP Power House Grand Prairie Data Center Building 1: TDLR TABS2026016734 registers a 224,152-square-foot, two-story single-tenant Data Center Building 1 at 881 Miller Road, with estimated construction cost of $72.59 million and listed construction period April 2026 to April 2028..
Sources
Source evidence
Current position
Verified facts
Uncertainty