Texas data-centre project

Vantage Frontier / TX301–TX310, Shackelford County

Abilene, Shackelford · construction. Source-backed view of project status, participants, power and development evidence.

constructionAbilenePRC-015
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
4Sources
4Verified facts
8Recent updates
2Phases tracked

Decision brief

What changed

Latest source-backed movement
Verified project fact updated

critical it capacity: 1,400 MW critical IT campus capacity.

Verified project fact updated

available power: 115 MW power capacity stated available by Oracle.

Research question opened for PRC-015

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Campus / ITRecorded power claim
capacityit load
Campus / ITRecorded power claim
capacitynot applicable
Campus / IT1,400 MW critical IT campus capacity
capacityit load
Campus / IT115 MW power capacity stated available by Oracle
capacitynot applicable

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

8 updates
Verified project fact updated

critical it capacity: 1,400 MW critical IT campus capacity.

Verified project fact updated

available power: 115 MW power capacity stated available by Oracle.

Research question opened for PRC-015

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Research question opened for PRC-015

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-015

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-015 requires analyst attention: missing linked evidence.

Advanced tracker status lacks evidence-backed status history

PRC-015 requires analyst attention: advanced status without history.

Advanced project has no canonical phase records

PRC-015 requires analyst attention: advanced status without phases.

Current position

Verified facts

4 verified
capacityVerified project fact
capacityVerified project fact
capacity1,400 MW critical IT campus capacity
capacity115 MW power capacity stated available by Oracle