Project Kilby / Microsoft Pecos data center campus
Reeves · identified. Source-backed view of project status, participants, power and development evidence.
identifiedReevesPRC-079
Evidence positionLimited evidenceReflects the strength of evidence supporting the current project status.
1Sources
3Verified facts
3Recent updates
0Phases tracked
Decision brief
What changed
Latest source-backed movement
Kilby power structure verified
Chevron primary evidence verifies Microsoft as the data-center operator, a 20-year PPA and approximately 2.67 GW of co-located generation; 2028 first power remains a target pending FID.
Research question opened for PRC-079
Project has no verified linked evidence. What authoritative evidence resolves this?
Generation / BTMChevron states Project Kilby is expected to deliver approximately 2.67 GW of co-located generation capacity.
power capacitygross generation
Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.
Latest intelligence
Project change log
3 updates
Kilby power structure verified
Chevron primary evidence verifies Microsoft as the data-center operator, a 20-year PPA and approximately 2.67 GW of co-located generation; 2028 first power remains a target pending FID.
Research question opened for PRC-079
Project has no verified linked evidence. What authoritative evidence resolves this?