Texas data-centre feed
What changed
Chevron primary evidence verifies Microsoft as the data-center operator, a 20-year PPA and approximately 2.67 GW of co-located generation; 2028 first power remains a target pending FID.
SEC filing verifies CleanSpark Data I completed the Brazoria land-rights acquisition on 2026-02-27; ~300 MW power framework and potential ~600 MW expansion remain development capacity, not energized/grid-secured.
Six building identities are now represented as canonical phases from primary TDLR records. Status remains identified at phase level because TDLR registration alone is not proof of construction or energization.