← All projectsPource Data Centre Intelligence · PRC-074

Texas data-centre project

Crusoe Goodnight / Llano campus, Claude

10001 Lima Rd, Claude, TX 79019, Armstrong · unknown. Source-backed view of project status, participants, power and development evidence.

unknown10001 Lima Rd, Claude, TX 79019PRC-074
Evidence positionEvidence developingReflects the strength of evidence supporting the current project status.
10Sources
25Verified facts
8Recent updates
6Phases tracked

Decision brief

What changed

Latest source-backed movement
Goodnight/Llano six-building TDLR phase set canonicalized

Six building identities are now represented as canonical phases from primary TDLR records. Status remains identified at phase level because TDLR registration alone is not proof of construction or energization.

New source evidence

BALLOT MEMORANDUM

Verified project fact updated

Armstrong CAD account 00773-00400-28400-000000 ownership transition: The 2024 certified roll listed Andy Freeman as 100% appraisal-roll owner of account 00773-00400-28400-000000, Parcel/Seq 3490/1, 640.0000 acres; the 2025 roll lists GN DC1, LLC on that same account and parcel. This establishes a roll-level ownership transition between the two certified rolls, not the recorded conveyance instrument or exact deed date..

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Campus / ITArmstrong County agreement states Phase 1 was planned to consume up to 530 MW of electrical energy.
planned phase electrical usenot yet verified
Campus / IT260 MW full level of energization from May 2026 onward
capacity ramp milestonenot yet verified
Campus / IT150 MW projected load in April 2026
capacity ramp milestonenot yet verified
Campus / IT50 MW projected load in March 2026
capacity ramp milestonenot yet verified
Campus / IT260 MW
capacity mentionnot yet verified
Grid positionERCOT confirmed LLI-1898 met cited Planning Guide requirements on March 2, 2026
interconnection study milestonenot applicable
Grid positionLLI-1898
large load interconnection idnot applicable

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

8 updates
Goodnight/Llano six-building TDLR phase set canonicalized

Six building identities are now represented as canonical phases from primary TDLR records. Status remains identified at phase level because TDLR registration alone is not proof of construction or energization.

New source evidence

BALLOT MEMORANDUM

Verified project fact updated

Armstrong CAD account 00773-00400-28400-000000 ownership transition: The 2024 certified roll listed Andy Freeman as 100% appraisal-roll owner of account 00773-00400-28400-000000, Parcel/Seq 3490/1, 640.0000 acres; the 2025 roll lists GN DC1, LLC on that same account and parcel. This establishes a roll-level ownership transition between the two certified rolls, not the recorded conveyance instrument or exact deed date..

Verified project fact updated

Armstrong CAD account 00227-00400-28300-000100 ownership transition: The 2024 certified roll listed Tony M. Ollinger as 100% appraisal-roll owner of account 00227-00400-28300-000100 (then 420.7000 acres); the 2025 roll lists GN DC1, LLC on the same account at 384.7700 acres. This establishes a roll-level ownership transition between the two certified rolls, not the recorded conveyance instrument or exact deed date..

Verified project fact updated

GN DC1 LLC — Armstrong CAD account 00773-00400-28400-000000: 2025 Armstrong CAD lists GN DC1, LLC as 100% appraisal-roll owner of Parcel/Seq 3490/1, account 00773-00400-28400-000000, legal description AB 773 BLK B4 SUR 284 H&GN, 640.0000 acres..

Verified project fact updated

GN DC1 LLC — Armstrong CAD account 00715-00400-31800-000001: 2025 Armstrong CAD lists GN DC1, LLC as 100% appraisal-roll owner of Parcel/Seq 7771/1, account 00715-00400-31800-000001, legal description AB 715 BLK B4 SUR 318 H&GN, 100.0000 acres, situs Dead End Lima Road..

Verified project fact updated

GN DC1 LLC — Armstrong CAD account 00227-00400-28300-000100: 2025 Armstrong CAD lists GN DC1, LLC as 100% appraisal-roll owner of Parcel/Seq 4230/1, account 00227-00400-28300-000100, legal description AB 227 BLK B4 SUR 283 H&GN, 384.7700 acres..

Verified project fact updated

Goodnight Data Center Phase 1: Armstrong County agreement describes Phase 1 as four currently anticipated buildings on approximately 350 acres of unimproved land..

Sources

Source evidence

10 shown

Current position

Verified facts

25 verified
appraisal owner transitionThe 2024 certified roll listed Andy Freeman as 100% appraisal-roll owner of account 00773-00400-28400-000000, Parcel/Seq 3490/1, 640.0000 acres; the 2025 roll lists GN DC1, LLC on that same account and parcel. This establishes a roll-level ownership transition between the two certified rolls, not the recorded conveyance instrument or exact deed date.
appraisal owner transitionThe 2024 certified roll listed Tony M. Ollinger as 100% appraisal-roll owner of account 00227-00400-28300-000100 (then 420.7000 acres); the 2025 roll lists GN DC1, LLC on the same account at 384.7700 acres. This establishes a roll-level ownership transition between the two certified rolls, not the recorded conveyance instrument or exact deed date.
county appraisal parcel record2025 Armstrong CAD lists GN DC1, LLC as 100% appraisal-roll owner of Parcel/Seq 3490/1, account 00773-00400-28400-000000, legal description AB 773 BLK B4 SUR 284 H&GN, 640.0000 acres.
county appraisal parcel record2025 Armstrong CAD lists GN DC1, LLC as 100% appraisal-roll owner of Parcel/Seq 7771/1, account 00715-00400-31800-000001, legal description AB 715 BLK B4 SUR 318 H&GN, 100.0000 acres, situs Dead End Lima Road.
county appraisal parcel record2025 Armstrong CAD lists GN DC1, LLC as 100% appraisal-roll owner of Parcel/Seq 4230/1, account 00227-00400-28300-000100, legal description AB 227 BLK B4 SUR 283 H&GN, 384.7700 acres.
planned phase site areaArmstrong County agreement describes Phase 1 as four currently anticipated buildings on approximately 350 acres of unimproved land.
regulatory milestoneERCOT commenced its study on January 29, 2026
interconnection study milestoneERCOT confirmed LLI-1898 met cited Planning Guide requirements on March 2, 2026
large load interconnection idLLI-1898
filing type mentionPL
filing party mentionERCOT
filing type mentionPL
filing party mentionERCOT
filing type mentionPL
filing party mentionPUC OPDM
filing type mentionPL
filing party mentionPUC OPDM
filing type mentionPL
filing party mentionPUC OPDM
filing type mentionPL
filing party mentionPUC MARKET ANALYSIS
filing type mentionBR
filing party mentionBKV Corporation
filing type mentionBR
filing party mentionTEXAS COMPETITIVE POWER ADVOCATES

Uncertainty

Not yet verified

5
planned phase electrical useArmstrong County agreement states Phase 1 was planned to consume up to 530 MW of electrical energy.
capacity ramp milestone260 MW full level of energization from May 2026 onward
capacity ramp milestone150 MW projected load in April 2026
capacity ramp milestone50 MW projected load in March 2026
capacity mention260 MW