Circe Energy West Texas AI Infrastructure Campus / West Texas HPC Campus
UNVERIFIED — Permian Basin; exact county not publicly disclosed · identified. Source-backed view of project status, participants, power and development evidence.
identifiedUNVERIFIED — Permian Basin; exact county not publicly disclosedPRC-088
Evidence positionLimited evidenceReflects the strength of evidence supporting the current project status.
2Sources
1Verified facts
3Recent updates
0Phases tracked
Decision brief
What changed
Latest source-backed movement
Circe West Texas capacity claims normalized
First-party Circe pages support long-term 1.1 GW scale but conflict on 2026 launch capacity (10 MW versus 50 MW); conflict preserved.
Research question opened for PRC-088
Project has no verified linked evidence. What authoritative evidence resolves this?
Generation / BTMCirce states the West Texas campus scales to 1.1 GW by 2030; the source does not explicitly classify this as IT load, generation nameplate, or grid import.
power capacitynot applicable
Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.
Latest intelligence
Project change log
3 updates
Circe West Texas capacity claims normalized
First-party Circe pages support long-term 1.1 GW scale but conflict on 2026 launch capacity (10 MW versus 50 MW); conflict preserved.
Research question opened for PRC-088
Project has no verified linked evidence. What authoritative evidence resolves this?
power capacityCirce states the West Texas campus scales to 1.1 GW by 2030; the source does not explicitly classify this as IT load, generation nameplate, or grid import.