← All projectsPource Data Centre Intelligence · PRC-083

Texas data-centre project

Lacy Lakeview Data District / L2D2 / Lacy Lakeview Campus

McLennan · identified. Source-backed view of project status, participants, power and development evidence.

identifiedMcLennanPRC-083
Evidence positionLimited evidenceReflects the strength of evidence supporting the current project status.
1Sources
1Verified facts
3Recent updates
1Phases tracked

Decision brief

What changed

Latest source-backed movement
L2D2 current phase and power path normalized

Current Infrakey source states 170 MW Phase 1, 925 MW planned full build, HILCO agreement complete, construction planned Nov 2026 and Phase 1 energization planned late 2027; no physical-start promotion.

Research question opened for PRC-083

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-083 requires analyst attention: missing linked evidence.

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Campus / ITCurrent Infrakey page states 170 MW Phase 1 capacity planned for 2027 delivery.
planned capacitynot yet verified
EnergizedInfrakey states a HILCO utility agreement was completed in 2026; this is first-party evidence of a stated power path, not independent proof of energized capacity.
power pathnot applicable
Campus / ITCurrent Infrakey page states 925 MW total planned campus capacity, with full build-out planned for 2030.
planned capacitynot yet verified

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

3 updates
L2D2 current phase and power path normalized

Current Infrakey source states 170 MW Phase 1, 925 MW planned full build, HILCO agreement complete, construction planned Nov 2026 and Phase 1 energization planned late 2027; no physical-start promotion.

Research question opened for PRC-083

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-083 requires analyst attention: missing linked evidence.

Current position

Verified facts

1 verified
power pathInfrakey states a HILCO utility agreement was completed in 2026; this is first-party evidence of a stated power path, not independent proof of energized capacity.

Uncertainty

Not yet verified

2
planned capacityCurrent Infrakey page states 170 MW Phase 1 capacity planned for 2027 delivery.
planned capacityCurrent Infrakey page states 925 MW total planned campus capacity, with full build-out planned for 2030.