Texas data-centre project

CyrusOne — Bosque County (Thad Hill) campus; DFW10 / DFW11 / DFW17 / DFW17B / DFW17C

Clifton, Bosque · construction. Source-backed view of project status, participants, power and development evidence.

constructionCliftonPRC-018
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
1Sources
1Verified facts
8Recent updates
3Phases tracked

Decision brief

What changed

Latest source-backed movement
New source evidence

OR2026-024341 and Comptroller 15-day letter re qualifying large data center applications

Research question opened for PRC-018

Map Comptroller registrations LD646862 (C1 Bosque I) and LD459723 (C1 Bosque II LLC) to the exact PRC-018 parcels/buildings and determine whether each registration corresponds to DFW10, DFW11, DFW17, DFW17B or DFW17C. Do not use the AP-236 20 MW statutory threshold as project-specific energized or contracted capacity.

Verified project fact updated

contracted power: 400 MW contracted powered-land capacity: 190 MW Phase 1 + 210 MW Phase 2.

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Grid position400 MW contracted powered-land capacity: 190 MW Phase 1 + 210 MW Phase 2
capacitycontracted

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

8 updates
New source evidence

OR2026-024341 and Comptroller 15-day letter re qualifying large data center applications

Research question opened for PRC-018

Map Comptroller registrations LD646862 (C1 Bosque I) and LD459723 (C1 Bosque II LLC) to the exact PRC-018 parcels/buildings and determine whether each registration corresponds to DFW10, DFW11, DFW17, DFW17B or DFW17C. Do not use the AP-236 20 MW statutory threshold as project-specific energized or contracted capacity.

Verified project fact updated

contracted power: 400 MW contracted powered-land capacity: 190 MW Phase 1 + 210 MW Phase 2.

Research question opened for PRC-018

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Research question opened for PRC-018

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-018

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-018 requires analyst attention: missing linked evidence.

Advanced tracker status lacks evidence-backed status history

PRC-018 requires analyst attention: advanced status without history.

Current position

Verified facts

1 verified
capacity400 MW contracted powered-land capacity: 190 MW Phase 1 + 210 MW Phase 2