Texas data-centre project

Cipher Digital Stingray HPC data center

Andrews, Andrews · construction. Source-backed view of project status, participants, power and development evidence.

constructionAndrewsPRC-078
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
1Sources
2Verified facts
6Recent updates
1Phases tracked

Decision brief

What changed

Latest source-backed movement
Research question opened for PRC-078

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-078

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-078 requires analyst attention: missing linked evidence.

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Grid position100 MW gross ERCOT-approved interconnection
capacitygrid import
Grid position70 MW contracted critical IT to AWS
capacitycontracted

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

6 updates
Research question opened for PRC-078

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-078

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-078 requires analyst attention: missing linked evidence.

Advanced tracker status lacks evidence-backed status history

PRC-078 requires analyst attention: advanced status without history.

Verified project fact updated

contracted it: 70 MW contracted critical IT to AWS.

Verified project fact updated

approved interconnection: 100 MW gross ERCOT-approved interconnection.

Current position

Verified facts

2 verified
capacity100 MW gross ERCOT-approved interconnection
capacity70 MW contracted critical IT to AWS