← All projectsPource Data Centre Intelligence · PRC-063

Texas data-centre project

Meta El Paso data-center campus / Wurldwide LLC

El Paso, El Paso · construction. Source-backed view of project status, participants, power and development evidence.

constructionEl PasoPRC-063
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
2Sources
3Verified facts
8Recent updates
2Phases tracked

Decision brief

What changed

Latest source-backed movement
Verified project fact updated

support generation: 366 MW ERock generation facility under construction for El Paso Electric.

Verified project fact updated

campus demand: Approximately 1,000 MW announced campus demand.

Research question opened for PRC-063

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Campus / ITRecorded power claim
capacityit load
Campus / ITApproximately 1,000 MW announced campus demand
capacitynot applicable
Generation / BTM366 MW ERock generation facility under construction for El Paso Electric
generation capacitygross generation

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

8 updates
Verified project fact updated

support generation: 366 MW ERock generation facility under construction for El Paso Electric.

Verified project fact updated

campus demand: Approximately 1,000 MW announced campus demand.

Research question opened for PRC-063

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Research question opened for PRC-063

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-063

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-063 requires analyst attention: missing linked evidence.

Advanced tracker status lacks evidence-backed status history

PRC-063 requires analyst attention: advanced status without history.

Advanced project has no canonical phase records

PRC-063 requires analyst attention: advanced status without phases.

Current position

Verified facts

3 verified
capacityVerified project fact
capacityApproximately 1,000 MW announced campus demand
generation capacity366 MW ERock generation facility under construction for El Paso Electric