Texas data-centre project
Meta El Paso data-center campus / Wurldwide LLC
El Paso, El Paso · construction. Source-backed view of project status, participants, power and development evidence.
constructionEl PasoPRC-063
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
2Sources
3Verified facts
8Recent updates
2Phases tracked
Decision brief
What changed
Latest source-backed movement
Verified project fact updatedsupport generation: 366 MW ERock generation facility under construction for El Paso Electric.
Verified project fact updatedcampus demand: Approximately 1,000 MW announced campus demand.
Research question opened for PRC-063Advanced project has no canonical phase records. What authoritative evidence resolves this?
Power & capacity
MW without the ambiguity
Each figure keeps its evidence classCampus / ITRecorded power claimcapacityit load
Campus / ITApproximately 1,000 MW announced campus demandcapacitynot applicable
Generation / BTM366 MW ERock generation facility under construction for El Paso Electricgeneration capacitygross generation
Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.
Latest intelligence
Project change log
8 updatesVerified project fact updatedsupport generation: 366 MW ERock generation facility under construction for El Paso Electric.
Verified project fact updatedcampus demand: Approximately 1,000 MW announced campus demand.
Research question opened for PRC-063Advanced project has no canonical phase records. What authoritative evidence resolves this?
Research question opened for PRC-063Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?
Research question opened for PRC-063Project has no verified linked evidence. What authoritative evidence resolves this?
Project has no verified linked evidencePRC-063 requires analyst attention: missing linked evidence.
Advanced tracker status lacks evidence-backed status historyPRC-063 requires analyst attention: advanced status without history.
Advanced project has no canonical phase recordsPRC-063 requires analyst attention: advanced status without phases.
Current position
Verified facts
3 verifiedcapacityVerified project fact
capacityApproximately 1,000 MW announced campus demand
generation capacity366 MW ERock generation facility under construction for El Paso Electric