Pource · Data Centre Intelligence · Texas

Know which Texas data-centre projects are real — and what changed.

Pource tracks the land, power, ownership, development status, tenants and primary-source evidence behind Texas data-centre projects. It separates announced capacity from requested, studied, contracted, grid-secured, behind-the-meter and energized MW — so you can see what is actually supported by evidence.

Explore the market
88Active Texas projects
44Construction or later
50Texas counties tracked
Including history

Texas data-centre feed

Market archive

18 updates
Verified project fact updated

large load interconnection: LLI-2011.

PRC-017 · CyrusOne Freestone / DFW20A-B-C campusProject update
Verified project fact updated

campus demand: Approximately 1,000 MW announced campus demand.

PRC-063 · Meta El Paso data-center campus / Wurldwide LLCProject update
Verified project fact updated

approved interconnection: 100 MW gross ERCOT-approved interconnection.

PRC-078 · Cipher Digital Stingray HPC data centerProject update
Verified project fact updated

critical it capacity: 1,400 MW critical IT campus capacity.

PRC-015 · Vantage Frontier / TX301–TX310, Shackelford CountyProject update
Verified project fact updated

support generation: 366 MW ERock generation facility under construction for El Paso Electric.

PRC-063 · Meta El Paso data-center campus / Wurldwide LLCProject update
Verified project fact updated

planned campus capacity: 540 MW planned campus capacity across six facilities.

PRC-092 · Aligned Project Caprock / LBB-01Project update
Verified project fact updated

contracted power: 400 MW contracted powered-land capacity: 190 MW Phase 1 + 210 MW Phase 2.

PRC-018 · CyrusOne — Bosque County (Thad Hill) campus; DFW10 / DFW11 / DFW17 / DFW17B / DFW17CProject update
Verified project fact updated

available power: 115 MW power capacity stated available by Oracle.

PRC-015 · Vantage Frontier / TX301–TX310, Shackelford CountyProject update
Verified project fact updated

contracted it: 70 MW contracted critical IT to AWS.

PRC-078 · Cipher Digital Stingray HPC data centerProject update
Verified project fact updated

Hood County powered industrial site: Acquisition completed through a 50/50 Big Digital Energy / 10NetZero joint venture on 2026-07-20..

PRC-004 · Big Digital Energy Hood County (JV w/ 10NetZero); fka MawsonProject update
Verified project fact updated

Hood County site: Phased expansion to as much as 111 MW of grid capacity is explicitly subject to ERCOT validation..

PRC-004 · Big Digital Energy Hood County (JV w/ 10NetZero); fka MawsonProject update
Verified project fact updated

Hood County site: Existing natural-gas infrastructure could support behind-the-meter generation and total buildout up to 300 MW; potential total power only, not contracted, grid-secured, IT-load or energized MW..

PRC-004 · Big Digital Energy Hood County (JV w/ 10NetZero); fka MawsonProject update
Verified project fact updated

Abernathy Joint Venture: TeraWulf entire 50.1% membership interest was sold effective 2026-07-06; TeraWulf no longer holds equity in the Abernathy JV..

PRC-008 · Fluidstack / Abernathy JV, Abernathy TXProject update
Verified project fact updated

Hood County site: Issuer states the acquired site currently has 17 MW of operational power; this is site power, not energized data-centre IT load..

PRC-004 · Big Digital Energy Hood County (JV w/ 10NetZero); fka MawsonProject update
Verified project fact updated

QTS FTW1 DC1 Expansion: TDLR TABS2026022992 records a 147,946 sq ft expansion with scheduled 2026-07-01 start and 2027-10-01 completion; registration does not prove physical start..

PRC-011 · QTS Fort Worth (FTW1 campus)Project update
Verified project fact updated

planning envelope acres: 1,522.18 acres (Goodland Light Industrial zoning/planning envelope; not a fee-ownership or data-center footprint assertion).

PRC-001 · PowerHouse Texas campus (768-acre claim; "Red Oak" alias disputed)Project update
Verified project fact updated

CyrusOne Medina County campus power path: CyrusOne states the campus is to be served through dedicated transmission infrastructure designed specifically for the facility and funded by CyrusOne, with project transmission interconnection and power-delivery costs paid by CyrusOne. Exact serving agreement and project MW remain unverified..

PRC-065 · CyrusOne SAT14A / Castroville data centerProject update
Verified project fact updated

CyrusOne Medina County campus physical progress: CyrusOne states site preparation and grading are in progress and describes early earth-moving/grading work with the general contractor. This supports construction-stage physical site work but not commissioning or energization..

PRC-065 · CyrusOne SAT14A / Castroville data centerProject update