Texas data-centre project
GW Ranch — Pacifico private-grid hyperscale campus, Pecos County
Pecos · identified. Source-backed view of project status, participants, power and development evidence.
identifiedPecosPRC-075
Evidence positionLimited evidenceReflects the strength of evidence supporting the current project status.
1Sources
3Verified facts
3Recent updates
0Phases tracked
Decision brief
What changed
Latest source-backed movement
GW Ranch primary power evidence normalizedPrimary evidence establishes the private-grid architecture and separates 7.65 GW gas generation from storage/solar and future data-centre load.
Research question opened for PRC-075Project has no verified linked evidence. What authoritative evidence resolves this?
Project has no verified linked evidencePRC-075 requires analyst attention: missing linked evidence.
Power & capacity
MW without the ambiguity
Each figure keeps its evidence classGeneration / BTMPacifico states GW Ranch has TCEQ air-permit approval for up to 7.65 GW of gas-fired generation.generation capacitygross generation
Grid positionPacifico states GW Ranch will operate independently from the ERCOT grid and requires no new utility transmission lines.power pathnot applicable
Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.
Latest intelligence
Project change log
3 updatesGW Ranch primary power evidence normalizedPrimary evidence establishes the private-grid architecture and separates 7.65 GW gas generation from storage/solar and future data-centre load.
Research question opened for PRC-075Project has no verified linked evidence. What authoritative evidence resolves this?
Project has no verified linked evidencePRC-075 requires analyst attention: missing linked evidence.
Current position
Verified facts
3 verifiedgeneration capacityPacifico states GW Ranch has TCEQ air-permit approval for up to 7.65 GW of gas-fired generation.
site areaPacifico states the project spans 8,000+ acres in Pecos County.
power pathPacifico states GW Ranch will operate independently from the ERCOT grid and requires no new utility transmission lines.