← All projectsPource Data Centre Intelligence · PRC-070

Texas data-centre project

PowerPlay AI Greater Abilene BTM campus

Unincorporated Greater Abilene area; exact site undisclosed, Greater Abilene — exact county unverified · lead. Source-backed view of project status, participants, power and development evidence.

leadUnincorporated Greater Abilene area; exact site undisclosedPRC-070
Evidence positionLimited evidenceReflects the strength of evidence supporting the current project status.
1Sources
3Verified facts
3Recent updates
0Phases tracked

Decision brief

What changed

Latest source-backed movement
Research question opened for PRC-070

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-070 requires analyst attention: missing linked evidence.

PowerPlay AI discloses 400 MW BTM Abilene development

First-party evidence verifies a 400 MW BTM target for 2028 and land acquisition; exact site, JV partner, IPP and regulatory filings remain unresolved.

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
EnergizedInitial 400 MW of behind-the-meter power targeted for delivery in 2028; developer target only, not energized or grid-secured load.
power capacitybehind the meter

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

3 updates
Research question opened for PRC-070

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-070 requires analyst attention: missing linked evidence.

PowerPlay AI discloses 400 MW BTM Abilene development

First-party evidence verifies a 400 MW BTM target for 2028 and land acquisition; exact site, JV partner, IPP and regulatory filings remain unresolved.

Current position

Verified facts

3 verified
power capacityInitial 400 MW of behind-the-meter power targeted for delivery in 2028; developer target only, not energized or grid-secured load.
site controlFirst-party statement says site feasibility, infrastructure assessment, land assembly and acquisition are complete, but parcel/title/deed and exact site remain undisclosed.
power pathNatural-gas service agreements are progressing; preferred independent power producer remains unselected after an RFP.