Rowan first-party evidence confirms construction underway at its 300 MW stated Temple campus, 2027 operations target and an Oncor power partnership.
Riot first-party evidence confirms the 400 MW substation energized and Building A1 hashing; A2, B1 and B2 are the remaining initial-phase buildings.
First-party Stream evidence confirms DFW VII in Garland was formally commissioned, correcting stale construction status to operational and confirming Oncor as the on-site substation provider.
Duos first-party evidence verifies newly operational Lubbock EDC infrastructure at 1634 18th Street.
Duos first-party evidence verifies the Waco EDC as operational at 2101 W. Loop 340.