Texas data-centre project

Provident — Hillsboro (HEDC Airport Tract)

Hillsboro, Hill · planning. Source-backed view of project status, participants, power and development evidence.

planningHillsboroPRC-029
Evidence readinessEvidence developing38/100 · research completeness and source coverage
3Sources
2Verified facts
8Recent updates
1Open diligence questions

Investment readiness

What has actually been de-risked

Evidence status · not an investment recommendation
Land · Partially verified

Site 4/20 · ownership 0/15

Power · Partially verified

Power evidence 18/30

Construction · Verified

planning · status evidence 13/15

Tenant · Unverified

Tenant evidence 0/10

Financing · Unverified

No verified financing claim currently recorded

Pource synthesis

What the evidence says

Factual synthesis · not a forecast
Confirmed position

site control: As of the current City of Hillsboro project page retrieved September 2, 2026, approximately 300 acres of HEDC-owned land remain under contract to Provident; the City says the contract lasts through November 2026 and may be extended. This contradicts the reported August 2026 termination and no authoritative termination record was found. · site control: City of Hillsboro states approximately 300 acres of HEDC-owned land have been under contract to Provident since September 2024 while the project remains in due diligence.

Still unverified

Verify whether the reported August 2026 termination of Provident's HEDC land contract is reflected in an updated City/HEDC record; current City project page still describes the contract/due-diligence process.

Timeline movement

No evidenced schedule change is identified in the current record.

Decision brief

What changed

Latest source-backed movement
New source evidence

Provident Pulls Out Of Contract On EDC Property

Verified project fact updated

HEDC Airport Tract: Provident no longer had the approximately 300-acre HEDC industrial-park property under contract.

Project research updated

Primary municipal/regulatory sweep found no new defensible canonical fact; due-diligence status and 12-building contemplated build-out remain current.

Latest intelligence

Project change log

8 updates
New source evidence

Provident Pulls Out Of Contract On EDC Property

Verified project fact updated

HEDC Airport Tract: Provident no longer had the approximately 300-acre HEDC industrial-park property under contract.

Project research updated

Primary municipal/regulatory sweep found no new defensible canonical fact; due-diligence status and 12-building contemplated build-out remain current.

Project research updated

Current City record confirms HEDC tract remains under contract to Provident through November 2026; reported termination not promoted.

Verified project fact updated

HEDC former-airport tract: As of the current City of Hillsboro project page retrieved September 2, 2026, approximately 300 acres of HEDC-owned land remain under contract to Provident; the City says the contract lasts through November 2026 and may be extended. This contradicts the reported August 2026 termination and no authoritative termination record was found..

Project research updated

Added City of Hillsboro due-diligence/site-control evidence; kept planning pending primary confirmation of reported contract withdrawal.

Diligence question added

Verify whether the reported August 2026 termination of Provident's HEDC land contract is reflected in an updated City/HEDC record; current City project page still describes the contract/due-diligence process.

New source evidence

Hillsboro Provident Data Center Project

Current position

Verified facts

2 verified
site controlAs of the current City of Hillsboro project page retrieved September 2, 2026, approximately 300 acres of HEDC-owned land remain under contract to Provident; the City says the contract lasts through November 2026 and may be extended. This contradicts the reported August 2026 termination and no authoritative termination record was found.City of Hillsboro ↗
site controlCity of Hillsboro states approximately 300 acres of HEDC-owned land have been under contract to Provident since September 2024 while the project remains in due diligence.Source verification in progress