Texas data-centre project
Galaxy Project Merlin / McGregor AI & HPC campus
McGregor Industrial Park, McGregor, McLennan · approved. Source-backed view of project status, participants, power and development evidence.
approvedMcGregor Industrial Park, McGregorPRC-066
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
1Sources
2Verified facts
4Recent updates
0Phases tracked
Decision brief
What changed
Latest source-backed movement
Research question opened for PRC-066Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?
Research question opened for PRC-066Project has no verified linked evidence. What authoritative evidence resolves this?
Project has no verified linked evidencePRC-066 requires analyst attention: missing linked evidence.
Power & capacity
MW without the ambiguity
Each figure keeps its evidence classGrid positionApproximately 74 MW secured for the initial Merlin phasecapacitycontracted
Grid positionUp to 500 MW potential campus capacity subject to utility transmission upgradescapacitynot applicable
Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.
Latest intelligence
Project change log
4 updatesResearch question opened for PRC-066Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?
Research question opened for PRC-066Project has no verified linked evidence. What authoritative evidence resolves this?
Project has no verified linked evidencePRC-066 requires analyst attention: missing linked evidence.
Advanced tracker status lacks evidence-backed status historyPRC-066 requires analyst attention: advanced status without history.
Current position
Verified facts
2 verifiedcapacityApproximately 74 MW secured for the initial Merlin phase
capacityUp to 500 MW potential campus capacity subject to utility transmission upgrades