← All projectsPource Data Centre Intelligence · PRC-062

Texas data-centre project

Hedgehog USA Navarro County data-center campus

Rice, TX — approximately 1.35 miles south of downtown at NE 3270/1603 and I-45; 32.196400, -96.475628, Navarro · approved. Source-backed view of project status, participants, power and development evidence.

approvedRice, TX — approximately 1.35 miles south of downtown at NE 3270/1603 and I-45; 32.196400, -96.475628PRC-062
Evidence positionStrong evidenceReflects the strength of evidence supporting the current project status.
1Sources
1Verified facts
4Recent updates
0Phases tracked

Decision brief

What changed

Latest source-backed movement
Research question opened for PRC-062

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-062

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-062 requires analyst attention: missing linked evidence.

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
EnergizedHedgehog states planned data-center capacity up to 600 MW by end-2027; not energized or contracted IT.
capacitynot applicable

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

4 updates
Research question opened for PRC-062

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-062

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-062 requires analyst attention: missing linked evidence.

Advanced tracker status lacks evidence-backed status history

PRC-062 requires analyst attention: advanced status without history.

Current position

Verified facts

1 verified
capacityHedgehog states planned data-center capacity up to 600 MW by end-2027; not energized or contracted IT.