Texas data-centre project

CyrusOne Allen — DFW3–DFW5

Allen, Collin · energized. Source-backed view of project status, participants, power and development evidence.

energizedAllenPRC-046
Evidence positionLimited evidenceReflects the strength of evidence supporting the current project status.
1Sources
1Verified facts
8Recent updates
3Phases tracked

Decision brief

What changed

Latest source-backed movement
CyrusOne Allen identity corrected

Canonical row corrected from mixed Richardson/Allen identity to the Allen DFW3-DFW5 campus; DFW3+DFW4 have 77 MW combined IT capacity and DFW5 is landbank.

Research question opened for PRC-046

Sellable 25 — establish project-specific power entitlement by separating claimed IT MW, facility MW, requested MW, studied MW, contracted MW, grid-secured MW, switchyard/substation capacity and energized MW; identify TDU/TSP, LLI/interconnection IDs, study/service-agreement milestones and binding constraints.

Research question opened for PRC-046

Sellable 25 — establish titled land owner and enforceable site-control chain: parcel/account IDs, acreage, legal description, deeds/instruments, easements, prior owner, and developer/SPV control. Do not infer ownership from announcements.

Power & capacity

MW without the ambiguity

Each figure keeps its evidence class
Campus / ITRecorded power claim
capacityit load

Pource does not collapse announced, requested, studied, contracted, grid-secured, behind-the-meter and energized MW into a single capacity number.

Latest intelligence

Project change log

8 updates
CyrusOne Allen identity corrected

Canonical row corrected from mixed Richardson/Allen identity to the Allen DFW3-DFW5 campus; DFW3+DFW4 have 77 MW combined IT capacity and DFW5 is landbank.

Research question opened for PRC-046

Sellable 25 — establish project-specific power entitlement by separating claimed IT MW, facility MW, requested MW, studied MW, contracted MW, grid-secured MW, switchyard/substation capacity and energized MW; identify TDU/TSP, LLI/interconnection IDs, study/service-agreement milestones and binding constraints.

Research question opened for PRC-046

Sellable 25 — establish titled land owner and enforceable site-control chain: parcel/account IDs, acreage, legal description, deeds/instruments, easements, prior owner, and developer/SPV control. Do not infer ownership from announcements.

Research question opened for PRC-046

Advanced project has no canonical phase records. What authoritative evidence resolves this?

Research question opened for PRC-046

Advanced tracker status lacks evidence-backed status history. What authoritative evidence resolves this?

Research question opened for PRC-046

Project has no verified linked evidence. What authoritative evidence resolves this?

Project has no verified linked evidence

PRC-046 requires analyst attention: missing linked evidence.

Advanced tracker status lacks evidence-backed status history

PRC-046 requires analyst attention: advanced status without history.

Current position

Verified facts

1 verified
capacityVerified project fact